Moreton Terrace Renewal - Progress Update #15

News

24 August 2021

The focus is now on the final phase of upgrading the Terrace, from the Brand Highway into town, back to the Point Leander Drive roundabout plus asphalting the Hunt/Waldeck Street roundabout.

Aiming for the new streetlights to be switched on end of next week.

The 4 Stages of the renewal are as detailed below:

STAGE 1 COMPLETE

STAGE 2 CONTINUING
Asphalting from the Brand Highway to the Point Leander Drive roundabout is scheduled to start next week. Asphalting will be followed by kerbing and paving and associated groundworks.

STAGE 3 CONTINUING
Line marking and installation signage will follow the completion of all road works.

STAGE 4 CONTINUING
Garden reinstatement continues with re-planting garden beds is now underway.

Road closures will be kept to a minimum and the roadway will be opened as soon as it is safe to do so, with daily reviews. Traffic management will be in place throughout the works program to keep traffic flowing and pedestrians safe.

The Shire sincerely thanks the community for their cooperation during these works and apologises for any inconvenience.

For further information regarding the Moreton Terrace Upgrade works please contact the Shire Administration Office on 9927 0000 or email reception@irwin.wa.gov.au.

 