Moreton Terrace Renewal - Progress Update #12

Alerts

03 August 2021

Moreton Terrace Upgrade 

The work between the roundabouts is nearing completion with work to start on the Waldeck Street and Point Leander Drive roundabouts. This will require some partial and full road closures this week, commencing with a closure of the Waldeck Street roundabout followed by a closure of the Point Leander Drive roundabout. Traffic control will be in place to minimise disruption and help drivers follow detours as arrangements change day by day. Please contact the Visitors Centre for information about bus stop arrangements.
 
The 4 Stages of the renewal are as detailed below: 

STAGE 1 – COMPLETE  

STAGE 2 – CONTINUING 
Closures are required for formwork and concreting to be undertaken at both the Waldeck Street and Point Leander Drive roundabouts. 

The remaining road surface profiling and asphalting of the section beginning at the Point Leander roundabout and ending at the Brand highway will be re-scheduled according to the availability of the asphalting contractor. Asphalting at the roundabouts will also be undertaken at the same time. 

STAGE 3 – CONTINUING 
Paving in the section between the two roundabouts is nearing completion. Roundabout construction works will commence this week. Line marking and  signage installation will follow.  

STAGE 4 – COMMENCED  
Garden reinstatement has commenced, and streetlights are being prepared for installation this month. 

The Shire sincerely thanks the community for their cooperation during these works and apologises for any inconvenience.
 
For further information regarding the Moreton Terrace Upgrade works please contact the Shire Administration Office on 9927 0000 or email reception@irwin.wa.gov.au.  