Moreton Terrace Upgrade

News

21 April 2021

Works are soon to commence on upgrading the full length of Moreton Terrace including drainage, footpaths, lighting and road surfaces.

The bulk of the works are scheduled to commence Tuesday, 27 April. The entire project is planned to be completed by the 30 June 2021. Detailed drawings of the works can be obtained from the Shire Administration Office or the Shire webpage www.irwin.wa.gov.au. 

To assist residents and motorists, Traffic Management will be in place for the duration of the works. 

The works are staged in 4 main areas of work detailed below: 

STAGE 1 - Temporary fencing to allow for the removal of existing kerbs, lights and improve drainage points. New cables, conduits and irrigation will be trenched through the entire length of Moreton Terrace for upgrades to lighting and landscaping in Stage 4. 
STAGE 2 - New asphalt works including level changes for drainage requirements and realignment for parking bays and roundabouts. New kerbing will then be installed. 
STAGE 3 - New paving to all paths each side and reinstatement of any verges. Line marking and signage installed. 
STAGE 4 - Install light poles and reinstate gardens to verge areas and remove fencing. 

The Shire apologies for any inconvenience these works may cause.  

For further details of the Moreton Terrace Upgrade works please contact the Shire Administration Office on 9927 0000 or email reception@irwin.wa.gov.au. 